A third sinkhole has left the works in Orchard Street facing further delays.
Engineers uncovered the void during investigations this week, leaving traders facing an uncertain run-up to Christmas and further delays to the new street scene works.
Digging began by Eric Wright Group in the summer as part of the Friargate South works which are taking place in the area from the Flag Market, the Market Hall and Ringway.
Read more: Preston Christmas on Ice set up begins on Flag Market with SpudBros tram moved
Two sinkholes were uncovered during the first few weeks leading to a halt in works.
Traders said works began again but have ground to a halt this week due to the new void which is towards the Friargate end of Orchard Street close to the Roast deli and sandwich shop.
Norman Young, of Banana King, who has been a vocal critic of the way the works are being planned and carried out said his shop was now considering shutting until the works are complete.
He said: “It’s hit us hard and for most of us on Orchard Street these are crucial weeks of the year in the run up to the Christmas period.
“It’s not just us, all traders down here are being affected.
“It’s disappointing to see how the likes of McDonalds can have a walkway put in, but when we ask for similar, the response is it can’t be done. Yet it can be for these mega corporations with deep pockets.
“We’ve traded in the city centre since 1889 as a family business and it feels like the council isn’t taking seriously the issues this is causing.

Blog Preston understands at least one business on Orchard Street has been placed on the market due to plummeting takings during the roadworks and big national chains, like Greggs, are also being badly affected.
Work on Orchard Street appeared to have overcome the impasse reported on in September with the two voids tackled that were found, but Preston City Council confirmed a fresh one had been discovered leaving engineers looking for a fresh way around the problem.
Traders told Blog Preston when we visited the scene on Wednesday: “We don’t understand why they can’t finish the top end of the street, which looks like they are close to putting the paving down and get that sorted before they tackle the sinkhole and bottom end of the street.”


A statement from the city council released this week said: “As works to the public realm recommenced on Orchard Street last week, preparation works on the lower section of Orchard Street uncovered another void which will require further assessments.
“Work has been paused on the lower section of Orchard Street whilst the appropriate investigations are undertaken.
“Preston City Council are working closely with Eric Wright Civil Engineering and relevant stakeholders, including Lancashire County Council to outline the next steps. We apologise for any inconvenience this may cause.”
Mr Young was critical of the council’s statement, saying all work had halted – rather than just the lower section of Orchard Street.
Work on the Cheapside side of the Friargate South scheme and Market Street have seen road closures removed in recent weeks, and works on Friargate itself are continuing.
Earlier this month a new water feature appeared due to problems with a pipe system uncovered by engineers which sent a jet of water shooting up in the air near McDonalds on Friargate.
A business group, which represents city centre businesses and is funded by a levy on business rates, Preston Business Improve District says it is concerned about the impact on traders.
BID manager, Mark Whittle, told Blog Preston: “The latest sinkhole on Orchard Street is another significant setback for businesses that have already endured considerable disruption over an extended period.
“Small businesses are the lifeblood of the city centre and the ongoing works are having a very real impact on their ability to trade. We are increasingly concerned about the cumulative financial pressure this is placing on businesses, particularly independent operators who simply cannot sustain prolonged disruption and uncertainty.
“The BID is continuing to represent the interests of its members and has already written directly to the Leader of the Council to formally raise these concerns and call for meaningful support.
“We have specifically requested that the Council considers business rate reductions, backdated to reflect the period businesses have been affected, alongside a clear and transparent schedule of works so that businesses can plan and have some certainty about what lies ahead.
“We recognise that essential infrastructure works need to be undertaken, and are sure businesses would welcome the improved streetscape once completed, but they should not be left carrying the financial burden of delays, disruption and unforeseen issues that are outside their control.
“Our message to the Council is clear: businesses need more than assurance, they need practical support, clear communication and a realistic timetable for completing the works.
“We will continue to make the case on behalf of our members and push for the support that Orchard Street businesses urgently need.”
Support Blog Preston: Keep our community reporting going and view the website without any adverts too. Sign up for a membership today.
Stay updated: Keep in touch directly with the latest headlines from Blog Preston, join our WhatsApp channel and subscribe for our twice-a-week email newsletter. Both free and direct to your phone and inbox. Help us report too, by contacting us if you see something we should be reporting on.
Read more: See the latest Preston news and headlines
See us on Google: Set Blog Preston as your preferred source so you don’t miss our stories and see us first when you’re searching
Add Blog Preston as a preferred source on Google
All the festive and Christmas fun and events in and around Preston View collection
Each week Blog Preston editors Luke Beardsworth and Ed Walker break down the big talking points and stories in the city, plus our quick-fire round-up of good news. You can find Never Mind The Bollards on Apple, Spotify and YouTube - just search for it. View collection
City Centre Redevelopment
207 Articles
Preston - it’ll be great when it’s finished. View collection
Blog Preston has been going since 2009 and you can become a supporter to help us tell more stories about the city. Pay what you can, from £1 for a membership and support our local journalism.
Pay what you want
Did any of the the business owners, actually ask for Orchard Street to be re-paved? If not, business rates should be halted until the street is fully functioning again.
Again, we’re seeing the ineffectiveness of communication from Preston City Council. They’ve essentially issued an engineering update. Reasonable as far as it goes, but it doesn’t address the commercial consequences for businesses heading into what should be one of their busiest trading periods.
Businesses cannot plan around uncertainty, something the BID has rightly highlighted. Reports of businesses considering temporary closure or even selling up need to be taken seriously, although the precise circumstances and extent of the financial impact need to be established.
There are also perfectly legitimate questions around the original ground investigations and whether the discovery of the first two sinkholes prompted any wider reassessment of the area. What surveys were undertaken, how thorough were they, and were further potential problems identified?
I also seem to remember that concerns were raised when the project first started about the proposed timescale and what contingency arrangements existed should unexpected problems arise. If I recall correctly, the works were originally due to be completed next week.
If that was the original target, we’re now looking at a project that has encountered repeated setbacks, with local businesses bearing much of the commercial impact.
The council cannot necessarily prevent unforeseen engineering problems, but it should be able to demonstrate that it has planned for contingencies and, just as importantly, that it has a meaningful strategy to support the businesses affected.
At the start they should have surveyed the whole area with ground penetrating radar and excavated as necessary. Then they could consider civil engineering works. This would have taken 3 weeks maximum. A top team would have it all sorted in a month.