The refurbishment and bringing back into use of a decades-empty building in the heart of Preston city centre remains on track for summer next year.
Amounderness House, built in 1857, was used as a police station and magistrates’ court but has sat unused next to the Town Hall for decades.
Work began last autumn after a number of re-designs to the project to convert it into offices and co-working spaces were needed to keep costs down.
Preston City Council, along with Maple Grove Developments and Eric Wright Construction, say a ‘key milestone’ has now been reached with the completion of a mezzanine floor.
The grade-II listed building, which includes former prison cells, is being restored with period features retained within the listed buildings.
Project manager at Maple Grove, Nick Hague, said: “It’s great to be at Amounderness House and see the works continuing to progress at pace. Eric Wright Construction has made excellent progress over recent months, successfully navigating a number of unforeseen challenges that have arisen during the restoration of this historic listed building, which has been vacant for over 30 years.
“With the introduction of the new mezzanine floor, the new office space is really taking shape and I’m excited to see it continue over the coming months.”
The restoration project is due to see 26 offices, four studios and a dedicated meeting and event space created which Preston-based Wrkspace group is due to operate and run.
Deputy leader at the Labour-run administration, and cabinet member for community wealth building at the city council, councillor Valerie Wise, said: “It is fantastic to see the progress being made on the transformation of Amounderness House. The installation of the mezzanine deck is an important milestone, which complements the character of this historic building.
“I am equally committed to protecting the features that make Amounderness House so distinctive, including the former prison cells, its original cell doors, windows and brickwork. By combining sensitive restoration with high-quality modern facilities, the project will bring this important Grade II listed building back into use for many years to come.”
The project is now costing £10million – which has already jumped by £1million since work beginning – although Blog Preston understands this is contained within contingency funding set aside for the works.
Eric Wright Construction are overseeing the project, which has seen extensive scaffolding and hoarding put up along Earl Street and Lancaster Road near the city’s market, at the same time as also undertaking the nearby Friargate South street works.
Senior project manager at Eric Wright Construction, who are based in South Ribble, Dave Watson said: “As a joiner by trade it’s a pleasure to be working on a listed building, where traditional joinery has been used in the roof and windows. Our team have been hard at work delivering a very challenging and logistical project, and we are on track to complete in Spring 2027. The next phase of work will see us putting back an internal structure to the revised new build.”
The new Amounderness House is being part-funded by the city’s Towns Fund programme which secured £20million in 2021 to revitalise buildings in and around the Town Hall including the construction of the Animate cinema and leisure complex, the Vault Youth Zone and the renovation of the Harris Museum and Art Gallery.
Design work on Amounderness House was undertaken by Preston-based architects FWP who had to resubmit proposals a number of times due to revisions being made based on the historic building and scope of the project as it was reworked to keep costs down.
Mike Turner, FWP’s architectural lead on the project, told Blog Preston: “It’s great to see the project now reaching a stage where the transformation is becoming visible.
“Throughout the works, we’ve continued to carefully assess and preserve the building’s historic character wherever possible.
“While much of the original fabric was altered during refurbishments in the 1960s and 70s, features of real heritage value are being retained and restored.
“It’s rewarding to see these historic elements being brought back to life alongside the new interventions.”
Opening of the former prison and court house is due to take place in summer next year and marks a change in approach from the Town Hall who had previously attempted to offload the building.